Finally more track is being installed! New supports and track have been erected on top of the underground launch and break run tunnels - these tracks are continuing the section of F.L.Y. that was erected last summer and we have seen loads of photos.
The start of the launch has been lifted and fixed on to the ceiling. The launch part sticking out of the tunnel slopes upwards in the direction of the main road. The supports for the rest of the launch - the curved launch parts
@mrrc photographed at Vlodrop last year - have been erected.
The brake run has not been mounted on the ceiling yet.
The transfer tracks have now been completely enclosed and concrete is now being poured to form the roof.
Generally there is a lot of concrete work going on right now across the site.
A few more track parts and many more supports are also being stored on site awaiting erection.
Update source = Tobi on PhantaFriends.de